Saline River - AHTD

AHTD Job No. 070291  Saline River - South

The purpose of this project is to widen 5.68 miles of Hwy 167 in Dallas and Cleveland Counties to four lane divided or five lane undivided roadway. Mobley under Subcontract to Ideal Construction Company is constructing drainage structures including a double 10' x 8' R.C. Box Culvert that includes 1078 cubic yards of reinforced concrete, and four Continuous Concrete Girder Unit Bridges (Total Span Lengths 180', 180, 300, 240') that includes 2345 LF of 16" Square Concrete Piling, 4600 LF of 24" Square Concrete Piling, 2536 cubic yards of reinforced concrete, 30,520 lbs of structural steel, etc.  The project also includes the removal of the existing bridge structures once traffic is moved to the new bridge and roadway.

  


 

Contact Us

952 Highway 287
P.O. Box 150
Morrilton, AR 72110

(501) 354-2510